Source + trust record
Source checked as of September 18, 2026. Primary authority: EDD WSIN25-11 and active WSD25-05.
Check result: WSIN25-11 correctly announced the return to a spring AJCC certification schedule and an expected May 2027 submission cycle. EDD has since issued WSD25-05 as the current AJCC certification directive. The timeline notice is retained as historical context; WSD25-05 and current CWDB instructions control the certification process. This AI-assisted brief does not receive human legal or compliance review. Official sources control.
The timeline alert has now been followed by the actual AJCC certification directive
WSIN25-11 warned Local Boards that California was moving AJCC certification submissions back to the spring cycle and expected the next documentation to be due in May 2027. EDD has since issued WSD25-05, the current AJCC Comprehensive and Affiliate/Specialized Certification directive.
Current status: Treat WSIN25-11 as the timeline notice. Use active directive WSD25-05 for the certification requirements and process.
At a glance
Certification frequency
Every 3 years
Old pandemic-era timing
Fall submission
Restored timing
Spring
Next cycle signaled
May 2027
Executive takeaway
Federal regulations require Local Boards to conduct an independent and objective evaluation of their AJCCs at least once every three years. California had moved the certification-document submission schedule to the fall during the pandemic. After feedback from the 2024 certification cycle, CWDB decided to return to a spring deadline.
Why the calendar matters
AJCC certification requires more than filling out a form. Local Boards need time for site review, partner input, accessibility and baseline compliance assessment, continuous-improvement review, corrective actions where needed, and formal Local Board action. Moving the state submission back to spring changes when that local work must begin.
Operational considerations for WDBs
- Use WSD25-05 as the controlling certification guidance.
- Put the 2027 certification cycle on the Board and staff operating calendar now.
- Work backward from the state submission date for site assessments, documentation, corrective actions, and Board approval.
- Include comprehensive, affiliate, and specialized sites in the local inventory.
- Do not wait until spring 2027 to discover accessibility, MOU, operator-role, or continuous-improvement issues.
Source basis
Timeline notice: EDD WSIN25-11
Policy distinction: WSIN25-11 explains the timeline change. WSD25-05 controls the current certification requirements.